Nanjing Sembcorp Wastewater Treatment Plant (WWTP) Expansion Project

Activities Performed:
About 20,000m3/d wastewater from Sembcorp Chemical Industrial Park needs to be treated in order to meet local discharge standard. Easen, in association with the partner, No. 4 Railway Bureau was in charge of whole WWTP design review, equipment procurement and civil works. The WWTP process is: Pretreatment +Two-stage biological contact oxidation treatment.The effluent should meet: Class I, Chemical Industry Pollutants Discharge Standard ( DB32/939-2006)